I get bore when I see static graphs even though the data is dynamic. Those static graphs are not exciting. GANTT Chart is one example of static charts. I thought to infuse some dynamism to it. Here is the sample of the same.

The green part represents the time/day that is already consumed, red represents current time/day and yellow represents the time that is still left. This is quite simple in excel. Please refer the steps below.
1. Create a table as shown below

2. Make sure it has From and To-Date. Based on the current date compute Finished (Consumed) days, Current Day and Remaining number of days. This can be done by simple excel formula. Remeber =today() gives current date.
3. Select All the Data From Date to Left, and insert Stack Bar Chart.
4. Right click on the chart and click on Select Data.
5. Update Milestones column under horizontal axis. Under legend entries series, do not forget to keep the data in From Date, Finished, Current and Left order. Refer the figure below.

6. The Stack bar chart will look like this.

7. Select the cell Work A Start Date. Right Click, Select Format Cell. Under Number tab, select general and note down the number.

8. Now, select the horizontal axis, right click and select Format Axis. In Axis option, make minimum value as 41575.

After this graph will look something like the one shown below.

9. Now select From Date in graph, change settings to no color fill and no borders.
And Bingo!!! the final output will look similar to this

One can the color as per as his/her needs.
As the date changes, automatically all your calculated day value changes adding a tinge of dynamism and the same is captured in Dynamic Gantt Chart
The green part represents the time/day that is already consumed, red represents current time/day and yellow represents the time that is still left. This is quite simple in excel. Please refer the steps below.
1. Create a table as shown below
2. Make sure it has From and To-Date. Based on the current date compute Finished (Consumed) days, Current Day and Remaining number of days. This can be done by simple excel formula. Remeber =today() gives current date.
3. Select All the Data From Date to Left, and insert Stack Bar Chart.
4. Right click on the chart and click on Select Data.
5. Update Milestones column under horizontal axis. Under legend entries series, do not forget to keep the data in From Date, Finished, Current and Left order. Refer the figure below.
6. The Stack bar chart will look like this.
7. Select the cell Work A Start Date. Right Click, Select Format Cell. Under Number tab, select general and note down the number.
8. Now, select the horizontal axis, right click and select Format Axis. In Axis option, make minimum value as 41575.
After this graph will look something like the one shown below.
9. Now select From Date in graph, change settings to no color fill and no borders.
And Bingo!!! the final output will look similar to this
One can the color as per as his/her needs.
As the date changes, automatically all your calculated day value changes adding a tinge of dynamism and the same is captured in Dynamic Gantt Chart